Today I went to the house with two items in mind:
- Wait for the guy with the digger to get the driveway started and
- Be present when the electrical distributor would come to move the meter inside the house.
Digging
The guy was supposed to come at 07:30 in the morning, but at 07:00 I got a call that he was already there. So I had to rush to get there and call our guy to let him know. So at 07:30 the work started and it was finished in about two hours. Cool! We both thought it'd take longer.
Electricity
The distributor was supposed to come between 13:30 and 15:30. Unfortunately, around 15:30 I got a phone call that they were at the corner of the road. When I went there, I couldn't see anyone and a bit later I got another phone call saying that the workers left and they would come 'tomorrow'. Enter panic mode.
I called the distributor and confirmed (sort of) verbally they would indeed come the next day. As we did not get a confirmation, we were still a bit stressed.
State of the house
The house state today is:
- [x] Paint
- [x] Parquet
- [x] Tiles
- [x] Security
- [ ] Doors (60%)
- [x] Ordered entrance door
- [ ] Install entrance door
- [x] Ordered interior doors (5)
- [ ] Order rest of the doors
- [ ] Install the 5 doors
- [ ] Install the rest of the doors
- [x] Ordered glass for the railings
- [x] Install glass for railings
- [x] Ordered replacement for broken window
- [x] Install replacement broken window
- [ ] Carpentry
- [ ] First flight of stairs
- [ ] Second flight of stairs
- [x] Black finishes walls
- [x] Black finishes windows
- [ ] Plumbing (70%)
- [x] Install plumbing
- [x] Install floor heating
- [x] Install the heat pump elements
- [x] Connect the interior/exterior heatpump elements
- [x] Perform final checkup of the heat pump
- [x] Perform mise en route (aka start + warranty)
- [ ] Integration with KNX
- [x] Install bathroom
- [ ] Install sinks upstairs
- [ ] Install sink downstairs
- [ ] Shower panels downstairs
- [ ] Shower panel upstairs
- [ ] Ventilation (70%)
- [x] Install ventilation pipes
- [x] Install ventilation machine Zehnder 350Q
- [ ] Intake, exhaust filters
- [ ] Optional increase the capacity of the ventilation system (PEB)
- [ ] Electricity (50%)
- [x] Cables are laid
- [x] High power electrical panel connections
- [x] KNX panel modules for lights installed
- [ ] KNX panel modules for heating installed
- [ ] KNX line couplers and interface installed
- [x] KNX wall bus couplers (200800)
- [ ] KNX switches (including frames)
- [ ] Test lights
- [ ] KNX programmed
- [ ] Lights - about 50% of them are done.
- [ ] Meter moved inside (75%)
- [x] Application
- [x] Quote
- [x] Scheduled date
- [ ] Execution
- [ ] IT
- [ ] WiFi Installation
- [ ] Cables from the panel to IT room
- [ ] Second rack
- [ ] Infra installation
- [ ] Network config
- [ ] Domain config
- [ ] Website config
- [ ] HA config
- [ ] Final operations (25%)
- [ ] Clean the house
- [x] Clean the outside
- [ ] Pathway
- [ ] Driveway
Member discussion: