Today is the day where the electricity distributor comes in. In the morning I confirmed (again) they would arrive.
... And so they did, almost one hour earlier than they said :)
They did great work and now all electricity works are done! Woo-hoo!
We installed the big window and figured out that we need a top light because the strip won't provide too much light.
State of the house
The house state today is:
- [x] Paint
- [x] Parquet
- [x] Tiles
- [x] Security
- [ ] Doors (70%)
- [x] Ordered entrance door
- [ ] Install entrance door
- [x] Ordered interior doors (5)
- [ ] Order rest of the doors
- [x] Install the 5 doors
- [ ] Install the rest of the doors
- [x] Ordered glass for the railings
- [x] Install glass for railings
- [x] Ordered replacement for broken window
- [x] Install replacement broken window
- [ ] Carpentry
- [x] First flight of stairs
- [ ] Second flight of stairs
- [x] Black finishes walls
- [x] Black finishes windows
- [ ] Vinyl parquet basement
- [ ] Plumbing (70%)
- [x] Install plumbing
- [x] Install floor heating
- [x] Install the heat pump elements
- [x] Connect the interior/exterior heatpump elements
- [x] Perform final checkup of the heat pump
- [x] Perform mise en route (aka start + warranty)
- [ ] Integration with KNX
- [x] Install bathtub
- [ ] Install sinks upstairs
- [ ] Install sink downstairs
- [ ] Shower panels downstairs
- [ ] Shower panel upstairs
- [ ] Ventilation (70%)
- [x] Install ventilation pipes
- [x] Install ventilation machine Zehnder 350Q
- [ ] Intake, exhaust filters
- [ ] Optional increase the capacity of the ventilation system (PEB)
- [ ] Electricity (50%)
- [x] Cables are laid
- [x] High power electrical panel connections
- [x] KNX panel modules for lights installed
- [ ] KNX panel modules for heating installed
- [ ] KNX line couplers and interface installed
- [x] KNX wall bus couplers (200800)
- [ ] KNX switches (including frames)
- [x] Test lights
- [ ] KNX programmed
- [ ] Lights - about 50% of them are done.
- [x] Meter moved inside
- [x] Application
- [x] Quote
- [x] Scheduled date
- [x] Execution
- [ ] IT
- [ ] WiFi Installation
- [ ] Cables from the panel to IT room
- [ ] Second rack (50%)
- [x] Buy
- [ ] Install
- [ ] Infra installation
- [ ] Network config
- [ ] Domain config
- [ ] Website config
- [ ] HA config
- [ ] Final operations (25%)
- [ ] Clean the house
- [x] Clean the outside
- [ ] Pathway
- [ ] Driveway
- [ ] Finishes
- [x] Install big mirror
- [ ] Install the swivel cabinet
- [ ] Soap holder ground floor
- [ ] Soap holder first floor
- [ ] Cabinet between the sinks first floor
- [ ] Storage cabinet first floor
Member discussion: