House log - 15/12/21
1 min read

House log - 15/12/21

House log - 15/12/21

Today, despite some unfinished bits in the house, we did the removal. The removal company was OK, but a bit negligent.

We had Nichita doing a sleepover so we can fix the house, which helps because of the home schooling and stuff.

State of the house

The house state today is:

  • [x] Paint
  • [x] Parquet
  • [x] Tiles
  • [x] Security
  • [ ] Doors (80%)
    • [x] Ordered entrance door
    • [x] Install entrance door
    • [x] Ordered interior doors (5)
    • [x] Install the 5 doors
    • [ ] Order rest of the doors
    • [ ] Install the rest of the doors
    • [x] Ordered glass for the railings
    • [x] Install glass for railings
    • [x] Ordered replacement for broken window
    • [x] Install replacement broken window
  • [ ] Plumbing (90%)
    • [x] Install plumbing
    • [x] Install floor heating
    • [x] Install the heat pump elements
    • [x] Connect the interior/exterior heat pump elements
    • [x] Perform final checkup of the heat pump
    • [x] Perform mise en route (aka start + warranty)
    • [ ] Integration with KNX
  • [ ] Ventilation (70%)
    • [x] Install ventilation pipes
    • [x] Install ventilation machine Zehnder 350Q
    • [ ] Intake, exhaust filters - partially done,
    • [ ] Start the ventilation
    • [ ] Optional increase the capacity of the ventilation system (PEB)
  • [ ] Electricity (50%)
    • [x] Cables are laid
    • [x] High power electrical panel connections
    • [x] KNX panel modules for lights installed
    • [x] KNX panel modules for heating installed
    • [x] KNX line couplers and interface installed
    • [x] KNX wall bus couplers (200800)
    • [ ] KNX programmed
      • [x] Lights cellar
      • [x] Lights ground floor
      • [x] Lights first floor
      • [ ] Heating cellar
      • [ ] Heating ground floor
      • [ ] Heating first floor
    • [x] Lights - All lights we bought are installed

HTH,